Section 571.23.12. Payments.  


Latest version.
  •        23.12(1) Grant amount. Grant recipients will be paid 75 percent of all eligible costs incurred on a project up to the amount of the grant unless otherwise specified in the project agreement.

           23.12(2) Project billings. Grant recipients shall submit billings for reimbursements or cost-sharing on forms provided by the commission.

           23.12(3) Project billing frequency. Project billings for development shall be submitted on the following basis:

            a.           Up to $10,000 total project cost—one billing.

            b.           Over $10,000 total project cost—no more than two billings.

           23.12(4) Final project billing. A final project billing shall be submitted within 90 days following the end of a project period. Failure to do so may be cause for termination of the project with no further reimbursement to the grant recipient.

           23.12(5) Documentation. Grant recipients shall provide documentation as required by the department to substantiate all costs incurred on a project.

           23.12(6) Reimbursement withheld. Ten percent of the total reimbursement due any grant recipient for a development project will be withheld pending a final site inspection or until any irregularities discovered as a result of a final inspection have been resolved.

           23.12(7) Acquisition projects. If clearly requested in the project application and the applicant has shown good cause for such procedure, the department may approve direct payment to the seller of the state’s share provided that marketable fee simple title, free and clear of all liens and encumbrances or material objections, is obtained by the local entity at the time of payments and state funds are then available.

           23.12(8) Development projects. On approved development projects, payment will be made by the state only as reimbursement for funds already expended by the local entity.